In an effort to remain a destination district in Northeast Ohio, as well as respond to the continuous community growth, Perrysburg Schools of Perrysburg, Ohio, embarked on a five-year plan to upgrade all their facilities.
The Collaborative, along with TMP Architecture, led the design and construction of a new 5th and 6th grade facility to house 900 students in a 130,000-square-foot building. The new building provides a more open and diverse learning environment and in doing so, reinvents the way the district teaches, by increasing access between students and teachers.
The flexible teaching spaces and innovative social areas allow for more creative interactions among students and teachers and help foster a better learning environment. The new building includes 32 classrooms, four special education classrooms, and two technology labs.
An exploratory cluster completes the heart of the building, with band rehearsal studios, orchestra rehearsal spaces, visual arts, and stage production areas open to the dining zone.
Hull Prairie Intermediate School provides an open and diverse learning experience that has updated the ways schools are built. The results make Hull Prairie Intermediate School a destination school for students seeking innovation and change in their learning.
Architect
The Collaborative – TMP
1 Seagate Place, #118, Toledo, OH 43604
www.thecollaborativeinc.com
Project Team
Structural Engineer
LKL Engineers
2735 N. Holland Sylvania Road, #2A, Toledo, OH 43615
Mechanical & Electrical Engineer
JDRM
5604 Main Street, #200, Sylvania, OH 43560
Construction Manager
Gilbane
950 Main Avenue, #1410, Cleveland, OH 44113
Cost Estimator
Swint Consulting
2550 Drummond Road, Toledo, OH 43606
Project General Description
Location: Perrysburg, Ohio
Date Bid: Mar 2015
Construction Period: Apr 2015 to Aug 2016
Total Square Feet: 131,307
Site: 18 acres
Number of Buildings: One; 36 classrooms; seating 28 per
classroom; seating 900 gymnasium.
Building Sizes: First floor, 94,670; second floor, 36,637;
total, 131,307 square feet
Building Height: First floor, 15′; second floor, 17′; total, 32′
Basic Construction Type: New/Steel Frame
Foundation: Cast-in-place, slab-on-grade
Exterior Walls: Brick, curtain wall, EIFS
Roof: Membrane. Floors: Concrete.
Interior Walls: Metal stud drywall, CMU
Simpl•EST Case Number EU250927
To access the project cost data in Simpl•EST Square Foot, enter “EU250927” into the Case Number search field located on the left side of your Simpl•EST dashboard.